Cost to Complete Financial report for closed jobs?

Posts about the simPRO API. Help/support/how-to etc.
Forum rules
  • Check the documentation first. Before posting questions, please check the documentation to ensure it doesn't already cover what you need.
  • No spam. All automated messages, advertisements, and links to competitor websites will be deleted immediately.
  • Post in relevant sub-forums only. Messages posted in the wrong topic area will be removed and placed in the correct sub-forum by moderators.
  • Respect other users. No flaming or abusing fellow forum members. Users who continue to post inflammatory, abusive comments will be deleted from the forum after two warnings are issued by moderators.
  • Harassment. No threats or harassment of other users will be tolerated. Any instance of threatening or harassing behavior is grounds for deletion from the forums.
  • Adult content. No profanity or pornography is allowed. Posts containing adult material will be deleted.
  • Bandwidth. All images and signatures must be 500 x 500 pixels or smaller. Posts containing over-sized images and signatures will be removed.
  • Illegal content. No re-posting of copyrighted materials or other illegal content is allowed. Any posts containing illegal content or copyrighted materials will be deleted.
Post Reply
johann
Posts: 51
Joined: Tue Oct 16, 2018 11:19 pm

Cost to Complete Financial report for closed jobs?

Post by johann » Wed Mar 10, 2021 8:12 am

I know by definition "Cost to complete" seems to infer only open jobs are not completed yet. :-)

But there is a date parameter in the endpoint to see what the values were at a certain point in time.

If I set the date parameter to a date when a specific project was still open, I would expect to see the values as it would've been at that time? But unfortunately it doesn't. It seems that as soon as a job is closed it's impossible to get any values for it from the report endpoint.

Would there be any way to allow historical values to be queried?

Thanks!
Johann
Wink Reports
Muqeet
Posts: 772
Joined: Mon Dec 03, 2018 3:24 am

Re: Cost to Complete Financial report for closed jobs?

Post by Muqeet » Wed Mar 10, 2021 11:37 pm

Unfortunately there is no report available which would give you historical values for closed jobs. In addition to that, we don't have plans to extend reporting functionality through rest api.
Muqeet
API Developer | simPRO Software Group
johann
Posts: 51
Joined: Tue Oct 16, 2018 11:19 pm

Re: Cost to Complete Financial report for closed jobs?

Post by johann » Thu Mar 11, 2021 12:06 am

Hi Muqeet,

Well, can you maybe give us some guidance then to help us figure out exactly how to calculate the costs? We're not new to the simPRO API as you know, but have tried several times in the past to try and come up with the same costs values as what is listed in the jobs without success.

We have some clients who run very long projects over many months and want to be able to work out the costs let's say for only a single month.

If you don't know the exact calculation, can you maybe ask around from the core team? Surely there's a query somewhere which you can post in pseudocode... eg.

For "Actual Costs" during February, calculate:
1. All scheduled visits by technician - their hours * rate (which you can get from api endpoint x and y)
2. All one-offs... you can find their date used in endpoint a, and their cost in endpoint b

I mean there must be some way to calculate it, since it's so fundamental to simPRO. :-)

Another option might be if there's associated costs listed for invoice items, or the invoice as a whole, in the customerInvoices endpoint?

Thanks,
Johann
Wink Reports
Muqeet
Posts: 772
Joined: Mon Dec 03, 2018 3:24 am

Re: Cost to Complete Financial report for closed jobs?

Post by Muqeet » Thu Mar 11, 2021 12:26 am

All scheduled visits by technician - their hours * rate (which you can get from api endpoint x and y)
Scheduled visits on a job for a set time period can be retrieved from the following endpoint and query parameters.

Code: Select all

/api/v1.0/companies/2/schedules/?Type=job&Reference={JobID}-%25&Date=between({StartDate YYYY-MM-DD},{EndDate YYYY-MM-DD})
All one-offs... you can find their date used in endpoint a, and their cost in endpoint b
That is not possible with current set of endpoints available. The only way to know if/when an item, one-offs etc is used, is by fetching jobs individually. There is no single endpoint which will give list of items and when and where it was used.
Muqeet
API Developer | simPRO Software Group
johann
Posts: 51
Joined: Tue Oct 16, 2018 11:19 pm

Re: Cost to Complete Financial report for closed jobs?

Post by johann » Thu Mar 11, 2021 6:24 am

Thanks Muqeet,

Me mentioning schedules and one-offs was just an example - I wasn't asking about just those 2 specicially. The point is, it's completely opaque as to how exactly totals are calculated - we don't even know which bits we're missing.

On the jobs endpoint you get for instance:

Code: Select all

"Totals": {
  "MaterialsCost": {
    "Actual": 1.57,
    "Committed": 1.57,
    "Estimate": 1.57,
    "Revised": 1.57,
    "Revized": 1.57
  },
"ResourcesCost": {
  "Total": {
    "Actual": 1.57,
    "Committed": 1.57,
    "Estimate": 1.57,
    "Revised": 1.57,
    "Revized": 1.57
  },
  "Labor": {},
  "LaborHours": {},
  "PlantAndEquipment": {},
  "PlantAndEquipmentHours": {},
  "Overhead": {}
  },
  
  ...etc
So my question is - how is Totals->MaterialsCost->Actual, and Totals->ResourcesCost->Total->Actual, and the others, calculated?

While these values are useful, we can only see them for the whole job up to the present. We can't see what eg the actuals were for February only on a job. And jobs can span many months. We'll have to recalculate it from scratch using all the other endpoints, but without knowing EXACTLY what goes into those totals, this seems like an almost impossible task.

Is there any way you can find out and tell us the calculations for those Totals fields? This must be available somewhere, as it's used everywhere inside the app.

Thanks,
Johann
Wink Reports
Muqeet
Posts: 772
Joined: Mon Dec 03, 2018 3:24 am

Re: Cost to Complete Financial report for closed jobs?

Post by Muqeet » Thu Mar 11, 2021 11:38 pm

Hello Johann,

The question about how job totals are calculated is more of a product question than api. You can contact simPRO support or the integration team and ask for any product related questions.
Muqeet
API Developer | simPRO Software Group