Posted: Fri Sep 18, 2020 8:24 am
Hi All
we are new to Simpro and we are manufacturing company. we do a lot of batch processing in some work stations, means we select different cost centres from different Job and run at the same time such as paint line. we run many products at the same time in the pain line form different projects.
SETUP - we set up Simpro as Projects = SIMPRO Jobs |Products = SIMPRO Cost centres ( each project and many manufacturer products inside )
Issue - as we know simpro have minimum 15min blocks and we wondering whether if we use custom made application and push data in which simpro allow us to post batch process time which some times less than 15min and different cost centers form different job in same time.
or is there any workaround to solve this issue ..
Please see below example
Scenario
Our Staff member “A” who works in Paint line is process 3 cost centres from different JOBs form 10.00 AM to 10.30AM.
Work flow
1. Our draft application he log in
2. Select all the jobs and cost centres
3. Clock in job and when he finish clock out the job
And the application give a output as below
Employee Job Cost centre Labour code Date Start time Finish time Total Time on the job
A 10001 1001A Painting 20.09.2020 10.00 10.10 10min
A 10002 1001S Painting 20.09.2020 10.10 10.20 10min
A 1003 1001C Painting 20.09.2020 10.20. 10.30 10min
are able to push the above Data Table ?
we are new to Simpro and we are manufacturing company. we do a lot of batch processing in some work stations, means we select different cost centres from different Job and run at the same time such as paint line. we run many products at the same time in the pain line form different projects.
SETUP - we set up Simpro as Projects = SIMPRO Jobs |Products = SIMPRO Cost centres ( each project and many manufacturer products inside )
Issue - as we know simpro have minimum 15min blocks and we wondering whether if we use custom made application and push data in which simpro allow us to post batch process time which some times less than 15min and different cost centers form different job in same time.
or is there any workaround to solve this issue ..
Please see below example
Scenario
Our Staff member “A” who works in Paint line is process 3 cost centres from different JOBs form 10.00 AM to 10.30AM.
Work flow
1. Our draft application he log in
2. Select all the jobs and cost centres
3. Clock in job and when he finish clock out the job
And the application give a output as below
Employee Job Cost centre Labour code Date Start time Finish time Total Time on the job
A 10001 1001A Painting 20.09.2020 10.00 10.10 10min
A 10002 1001S Painting 20.09.2020 10.10 10.20 10min
A 1003 1001C Painting 20.09.2020 10.20. 10.30 10min
are able to push the above Data Table ?