Question re mobile triggers

Posts about the simPRO API. Help/support/how-to etc.
Forum rules
  • Check the documentation first. Before posting questions, please check the documentation to ensure it doesn't already cover what you need.
  • No spam. All automated messages, advertisements, and links to competitor websites will be deleted immediately.
  • Post in relevant sub-forums only. Messages posted in the wrong topic area will be removed and placed in the correct sub-forum by moderators.
  • Respect other users. No flaming or abusing fellow forum members. Users who continue to post inflammatory, abusive comments will be deleted from the forum after two warnings are issued by moderators.
  • Harassment. No threats or harassment of other users will be tolerated. Any instance of threatening or harassing behavior is grounds for deletion from the forums.
  • Adult content. No profanity or pornography is allowed. Posts containing adult material will be deleted.
  • Bandwidth. All images and signatures must be 500 x 500 pixels or smaller. Posts containing over-sized images and signatures will be removed.
  • Illegal content. No re-posting of copyrighted materials or other illegal content is allowed. Any posts containing illegal content or copyrighted materials will be deleted.
Post Reply
Michael
Posts: 13
Joined: Tue Feb 05, 2019 2:47 am

Question re mobile triggers

Post by Michael » Mon Jun 15, 2020 4:57 am

Hi Guys,

I have been working with several simPRO customers on fixitfaster integration

I have Question re mobile triggers

With the following set up

statues
“Travelling to Site” (with ignore status priority switched On)
“4a Job: In Progress”

mobile trigger:
“travelling” sets status to “Traveling to site” and (job stage to “In Progress”)\

Trigger:
“A job has been put in the in-progress list” sets to status “4a Job: In Progress”


Behaviour Im seeing,
if “4a Job: In Progress” has a higher priority then “Travelling to Site”, then status will always be “4a Job: In Progress” whenever clicking “start Travel” from mobile connect App. This is independent of whether to not “ignore status priority” is switched on for “Travelling to Site”

Is this expected behaviour, Im surprised that “ignore status priority” has no effect, or perhaps Im misunderstanding something?

Any help or clarification on this would be much appreciated.

Regards,
Michael
rick.lan
Posts: 274
Joined: Wed May 30, 2018 6:14 am

Re: Question re mobile triggers

Post by rick.lan » Mon Jun 15, 2020 6:19 am

Hi Michael,

We have just confirmed with other developers and it is a expected behaviour
The mobile trigger happens first, then the effect of that is that the “A job has been put in the in-progress list” tigger will fire. So that happens second. So the second one will be what you end up with.
Could you please PM us the URL so we can take a look of the setting just in case?

cheers,
Rick Lan
API Developer | simPRO Software Group
vaughan
Posts: 43
Joined: Wed May 30, 2018 6:14 am

Re: Question re mobile triggers

Post by vaughan » Tue Jun 16, 2020 12:28 am

Hi Michael,

To further clarify, the process would be:

mobile trigger:
“travelling” sets status to “Traveling to site” and (job stage to “In Progress”)

Does "travelling" have ignore status priority or a higher status that the current status?
Yes it has ignore status priority, so perform Update status and any stage update set.

At this point this interaction particular status update is now complete.

Trigger:
“A job has been put in the in-progress list” sets to status “4a Job: In Progress”

Does "4a Job: In Progress" have ignore status priority or a higher status that the current status?
Yes it has a higher status so perform Update status and any stage update set.

At this point this interaction particular status update is now complete.

You can see these the steps to determine each status and stage are independant of each other.
Michael
Posts: 13
Joined: Tue Feb 05, 2019 2:47 am

Re: Question re mobile triggers

Post by Michael » Tue Jun 16, 2020 3:49 am

Hi Vaughan and Rick,

Thanks for the quick response.

Just a further clarification

Why does automatic trigger “A job has been put in the in-progress list” get invoked, is it because mobile trigger "travelling" sets job-stage to "In Progress" which in turn causes the invocation of that trigger?

Thanks,
Michael